Share on LinkedInShare on LinkedIn

ARTICLE · 12 SEPTEMBER 2008

Case Law Review - Construction, Property & Real Estate (September 2008)

Cantillon Ltd v Urvasco Ltd - Already reported in BLR, in a piling dispute referred to adjudication, the defendant argued unsuccessfully that the adjudicator had breached the rules of natural justice.

United KingdomReal Estate and Construction

ADJUDICATION

Natural Justice

Cantillon Ltd v Urvasco Ltd [2008] 117 Con LR 1 TCC
Already reported in BLR, in a piling dispute referred to adjudication, the defendant argued unsuccessfully that the adjudicator had breached the rules of natural justice. The court held that if one party argued a point and the other failed to address it that was not the adjudicator's fault. In ascertaining what the dispute comprised, the claimant was not limited to matters raised before it crystallised. The court had to consider the severability, or separate enforceability, of different parts of the decision.

Construction Law Journal 2008 Vol.24 No.5 contains the following articles:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.