Can You Contract Out Of The Prevention Principle?

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In the Court of Appeal (CA) decision in North Midland Building Ltd v Cyden Homes Ltd [2018], the TCC judgment at first instance has been unanimously upheld.

United KingdomReal Estate and Construction

In the Court of Appeal (CA) decision in North Midland Building Ltd v Cyden Homes Ltd [2018], the TCC judgment at first instance has been unanimously upheld. The CA considered the extent to which parties are able to decide where the risk will lie if concurrent delay arises.

Background

In summary:

  • In 2009, Cyden appointed North Midland to design and build a house and associated buildings under a JCT Design and Build 2005 contract with bespoke amendments (the Contract).
  • The amendments to the standard wording included the addition of a bespoke clause 2.25.1.3 stating that any award of an extension of time would be (amongst other things) subject to the following provisos – "...that (a) the Contractor has made reasonable and proper efforts to mitigate such delay; and (b) any delay caused by a Relevant Event which is concurrent with another delay for which the Contractor is responsible shall not be taken into account...".