ARTICLE · 09 JANUARY 2025

Building Liability Orders: Fire Safety Breaches Gave Rise To "Relevant Liability" As A Result Of A Building Safety Risk

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

The Technology and Construction Court (TCC) issued the first High Court finding of "relevant liability" under the Building Safety Act 2022, clarifying procedures and implications for Building Liability Orders (BLOs) to hold developers accountable for building safety defects.

United KingdomReal Estate and Construction

The Technology and Construction Court (TCC) has handed down what is understood to be the first High Court finding of a "relevant liability", for the purposes of Building Liability Orders under the Building Safety Act 2022 (BSA). In this article, we discuss the significance of this decision, particularly how it clarifies the grounds for Building Liability Order (BLO) applications. We explore the implications of the court's findings on "relevant liability" and its potential to hold developers accountable for building safety defects.

In 381 Southwark Park Road RTM Company Ltd & Ors v Click St Andrews Ltd & Anor [2024], the Technology and Construction Court (TCC) held that:

  • The defendant, a rooftop developer, had committed fire and structural safety breaches which gave rise to a "building safety risk" under section 130(3)(b) of the BSA;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.