This case created a bit of a stir in December 2018 when the
Outer House of the Court of Session held that BOBNL would be able
to pursue SMGL under a collateral warranty granted in 2013
notwithstanding the fact that
practical completion had occurred some nine years before and it
was apparent that the defect had arisen more than five years
previously. This decision was reversed by the Court of Session last
month, with particular ramifications for those relying on
collateral warranties.
Facts
SMGL (the defender), a building contractor, entered into a
contract with Northburn Developments Ltd (Northburn) for the design
and construction of a retail park in Inverurie. The build was
completed in 2009. In June 2013, the site was acquired by BOBNL
(the pursuer), who obtained collateral warranties from the defender
dated 24 June and 28 August 2013. Prior to the pursuer's
acquisition of the site, the car park (which was part of the site)
had been subject to flooding that was