Alternative Dispute Resolution Provisions As Conditions Precedent To Litigation

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In Children's Ark Partnerships Ltd v Kajima Construction (Europe) UK Ltd and another [2022], the Technology and Construction Court (TCC) found that a contractual alternative dispute resolution (ADR)...

United KingdomReal Estate and Construction

In  Children's Ark Partnerships Ltd v Kajima Construction (Europe) UK Ltd and another [2022], the Technology and Construction Court (TCC) found that a contractual alternative dispute resolution (ADR) clause gave rise to a condition precedent to the commencement of litigation. However, the ADR provision in question was unenforceable due to its lack of "clarity and certainty".

Background

  • In 2004, Children's Ark Partnerships Ltd (the Claimant) entered into a construction contract with Kajima Construction (the First Defendant) for the design, construction and commissioning of the Royal Alexandra Hospital for Sick Children in Brighton. The Claimant had signed a Project Agreement of the same date with the NHS Hospital Trust for the design, building and financing of the redevelopment of the Hospital.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from