Adjudication Update – Mead General Building Ltd –v- Dartmoor Property Ltd

The TCC has recently looked again at the question of whether there should be a stay of execution of an adjudicator’s award where the successful party in the adjudication is insolvent.

United KingdomReal Estate and Construction

The TCC has recently looked again at the question of whether there should be a stay of execution of an adjudicator's award where the successful party in the adjudication is insolvent. In Mead General Building Ltd (subject to a Company Voluntary Arrangement) –v- Dartmoor Property Ltd [2009] EWHC200 (TCC), Mr Justice Coulson looked at the position of a company subject to a company voluntary arrangement (CVA). The courts had not previously considered this type of insolvency procedure although they have considered others such as administration, administrative receivership and liquidation.

Mead had been awarded just under £350,000 in an adjudication against Dartmoor. Dartmoor refused to pay. Mead applied to the TCC for enforcement of the award and Dartmoor resisted, one of the grounds being that Mead were subject to a CVA and therefore insolvent and unable to pay back any sums that might be awarded in the event of future arbitration.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from