Today's entry reports on the completion of special parliamentary procedure for the first application to be given consent under the Planning Act 2008.

Once upon a time, a company called Covanta Energy applied for permission to build an energy from waste plant at Rookery South near Bedford - on 5 August 2010, in fact. This was the first application to be accepted by the then Infrastructure Planning Commission (IPC) (but not the first to be made - it rejected the first application made to it, for an electric line in south Wales).

434 days later - 1 year, 2 months and 8 days - and following all the procedures for accepting, making representations on, examining and deciding applications under the Planning Act, the IPC gave consent to the project. That was 13 October 2011.