High Court Allows A Rare S.68 Challenge To Arbitral Award Due To Serious Irregularity

Macfarlanes LLP
Macfarlanes LLP
Contributor
Macfarlanes LLP

Macfarlanes LLP

Macfarlanes is a distinctive London-based law firm with a unique combination of services built and...

View firm profile
Explore more from Macfarlanes LLP

The substantive dispute arose under a ship repair contract between the Claimant and the Defendant, which incorporated general conditions of tender (the General Conditions).

United KingdomLitigation, Mediation & Arbitration

The High Court's recent decision in Mare Nova Incorporated v Zhangjiagang Jiushun Ship Engineering Co. Ltd [2025] EWHC 223 (Comm)provides a rare example of a party successfully challenging an arbitral award on the ground of serious irregularity.

Background

The substantive dispute arose under a ship repair contract between the Claimant and the Defendant, which incorporated general conditions of tender (the General Conditions).

In March 2021, the Claimant's vessel entered the Defendant's shipyard for repair works. The works were signed off by the Claimant's representative on 30 March 2021. However, shortly after the vessel left the shipyard, the crew detected a burning smell, and it was discovered that the Defendant had damaged the vessel's intermediate shaft bearing.