Conditional Contracts - When Is Time Of The Essence For Submitting A Planning Application, When And Who Can Terminate And Who Keeps The Deposit?

Irwin Mitchell
Irwin Mitchell
Contributor
Irwin Mitchell

Irwin Mitchell

Irwin Mitchell are legal experts that care. As one of the largest full-service law firms in the UK,...

View firm profile
Explore more from Irwin Mitchell

Discover how in-house legal teams are approaching litigation as a strategic tool, with insights from our Leading Litigator Report conducted with The Lawyer. Nearly seven in ten General Counsels now view litigation as either an operational necessity or strategic investment to protect intellectual property, defend reputation, and strengthen market position.

United KingdomLitigation, Mediation & Arbitration

The decision in Whitburn Estates Ltd v Thirteen Homes Ltd and another [2026] EWHC 1256 (Ch) is an important modern authority on conditional contracts for the sale of development land. The case concerns the consequences of a purchaser's failure to comply with a contractual obligation to submit a planning application within a specified period, and whether that failure entitled the seller to terminate the contract and retain a substantial deposit. The decision is particularly significant for developers, landowners, and property lawyers because it highlights the importance of carefully drafted conditions precedent and confirms that clear contractual deadlines will often be strictly enforced.

The judgment addresses several recurring issues in development transactions, including:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from