In this case, the claimant sought continuation of an injunction
restraining the defendant from acting as experts for a third party
in an ICC arbitration against the claimant. The case is
important because it clarifies the duty owed by experts to their
clients.
The claimant was a developer of a petrochemical plant ("the
Project"). The claimant engaged the first defendant
(in Asia) to provide expert services with respect to an arbitration
commenced by a contractor known as "the Works Package
Arbitration" relating to the Project. The first
defendant's scope of works included identifying and analysing
delay events and the root cause for the delays. In the
Works Package Arbitration, the contractor claimed additional costs
by reason of delays to its work, including the late release of
Issued For Construction ("IFC") drawings. The
IFC drawings were produced by the third party and the
claimant's position was that to the extent it was liable to pay
the contractor any