The Procurement Reform Act 2014 was passed in summer 2014, at
which point a small number of its provisions
came into force. On 28 September 2015 a number of additional
provisions were brought into force by the Procurement Reform (Scotland) Act 2014
(Commencement No. 1) Order 2015/331.
In particular, one of the provisions enables Scottish Ministers
to publish guidance about the selection of tenderers and the award
of contracts, including in relation to workforce matters. It is
anticipated that guidance will follow over the next few months.
Background
The Act, once in force, will set out requirements in relation to
a new tier of "regulated contracts", which have a value
below the EU public procurement thresholds and above specified
thresholds, though certain contracts are excluded from the scope of
the Act. The specified thresholds are currently £2 million
for public works contracts and £50,000 for other public
contracts.