Reduced capital costs, phased commissioning, fleet learning and factory fabrication make SMRs the future of clean, low-cost power
Other things being equal, an SMR should produce a unit of electricity at higher cost than a gigawatt-scale plant. That is the diseconomies of scale. Proponents accept the point but say other things are not equal. This briefing addresses those arguments and explains the four factors which SMR proponents advocate: lower cost of capital, phased commissioning, fleet learning and factory fabrication.
What are the implications for investors and policymakers?
Be realistic about the first units. The diseconomies of scale will not be overcome on a first-of-a-kind SMR. Fleet benefits, learning rates and even much of the cost-of-capital advantage from faster construction only fully crystallise with 'nth-of-a-kind' delivery.