ARTICLE · 11 JULY 2024

How Should Businesses Prepare For UK Private Finance Initiative Project Handbacks?

Osborne Clarke LLP
Osborne Clarke LLP
Contributor
Osborne Clarke LLP

Osborne Clarke LLP

About us Osborne Clarke is an international, full service law firm 1, headquartered in London. We...

View firm profile
Explore more from Osborne Clarke LLP

With many UK PPP/PFI contracts nearing expiry, parties should start preparations seven years prior. Key considerations include service continuity, potential re-procurement, and compliance with government guidelines to ensure smooth handovers and avoid disputes.

United KingdomGovernment, Public Sector

A growing number of UK PPP/PFI contracts (for the provision of public buildings, infrastructure and other assets) are coming to an end.

Current government guidance (with industry-approved updates likely to be issued soon) is that the parties should start preparing at least seven years before the expiry date – in itself an indication that there is a lot for the parties to do before the contract ends. As ever, there are nuances between delivery structures (vanilla PFI and NHS LIFT), sectors and the project vintage (when it was signed and the standard form or version of guidance that applied).

Given the cliff-edge nature of the fixed expiry date, the public sector needs to plan for "what comes next". What services need to be delivered and by whom (and whether a procurement process and/or a TUPE consultation needs to be run)?

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from