ARTICLE · 19 JUNE 2017

Going Nuclear On Damages

The UK Supreme Court has recently considered an authority's liability for damages in the case of a breach of public procurement rules and has concluded that a breach must be "sufficiently serious"...

United KingdomGovernment, Public Sector

Nuclear Decommissioning Authority v Energy Solutions EU Ltd (now called ATK Energy EU Ltd) [2017] UKSC 34

The UK Supreme Court has recently considered an authority's liability for damages in the case of a breach of public procurement rules and has concluded that a breach must be "sufficiently serious" for damages to be awarded. The Supreme Court also decided that an economic operator need not have raised its damages claim before the contracting authority enters into the contract in question.

Case details

The respondent, the Nuclear Decommissioning Authority ("NDA"), sought to contract for the decommissioning of 12 Magnox power stations ("the procurement").

ATK Energy EU Ltd ("ATK") as part of the unsuccessful consortium Reactor Site Solutions ("RSS") raised an action for damages claiming that, in running the Procurement, NDA had breached its obligations under the (applicable at the time in question) Public Procurement Directive 2004/18/EC ("the Directive")