On 25 November 2014, the UK government published its response to
its further consultation on changes to financial support for solar
PV projects which opened on 2 October 2014 and closed on 24 October
2014. The response introduces a 12 month grid delay grace period
applying in situations where a project, due to commission on or
prior to 31 March 2015, fails to reach commissioning due to
circumstances outside of a developer's control.
The further consultation considered the introduction of a
possible grid delay grace period of three months for new solar PV
capacity above 5MW under the Renewables Obligation, following the
decision to close the Renewables Obligation to new solar PV
generating stations above 5MW from 1 April 2015. Following the
responses received to the government's further consultation,
the government has decided to extend this period to 12 months with
projects qualifying for the grace period needing to commission and
have an accreditation date on or