Onshore wind projects are central to Scotland’s renewable energy ambitions, with an installed capacity of over 10.5GW (as of Q4 2025), and 18.1GW in the pipeline.

United KingdomEnergy and Natural Resources

This article was first published in The Herald.

Onshore wind projects are central to Scotland’s renewable energy ambitions, with an installed capacity of over 10.5GW (as of Q4 2025), and 18.1GW in the pipeline.

However, projects face a number of challenges during the consenting process which threaten to blow onshore wind off course.

Time

National Planning Framework 4 (”NPF4”) designates onshore wind exceeding 50MW capacity as ‘national development’. Designation as a national development means that the need for the development has already been established and its delivery should be facilitated.

Developments over 50MW require consent under Section 36 of the Electricity Act 1989 (”S.36 consent”) from Scottish Ministers before they can be built. Since NPF4 was adopted in February 2023, 3.2GW of onshore wind has been consented in Scotland. However, the average time for S.36 applications to be determined is over two years if a public local inquiry (”PLI”) is not needed, and almost

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from