This is the first time such a significant extension has been granted and in this blog we explore how it was pursued.

United KingdomEnergy and Natural Resources

Summary

The regime for Nationally Significant Infrastructure Projects (NSIPs) allows for Development Consent Orders (DCOs) to be granted for a set period of time (often 5 years), but only recently has it become clear that time limits can be extended to keep DCOs alive.

The Department for Business, Energy and Industrial Strategy (BEIS) recently (16 September 2021) granted a non-material change to extend the timescale for implementation of a DCO for a period of 5 years for a proposed gas-fired power station. This is the first time such a significant extension has been granted and in this blog we explore how it was pursued.

The applicant, C.GEN, secured a DCO in 2014 for a gas-fired power station in North Killingholme, which had an original lifespan of 7 years. Due to a variety of commercial factors in the intervening years, implementation of the consent was ultimately not possible within the original 7 year time frame. However, there was a keenness to preserve

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from