Share on LinkedInShare on LinkedIn

ARTICLE · 08 APRIL 2014

Planning Inspectorate Accept Application For Development Consent For Swansea Bay Tidal Lagoon

The Planning Inspectorate accepted Tidal Lagoon Swansea Bay’s application for development consent for the Swansea Bay Tidal Lagoon.

United KingdomEnergy and Natural Resources
Zyda Law
Zyda Law

Planning Inspectorate accept Application for Development Consent for Swansea Bay Tidal Lagoon

On 6th March 2014, the Planning Inspectorate accepted Tidal Lagoon Swansea Bay plc (TLSB)'s application for development consent for the Swansea Bay Tidal Lagoon. An application is 'accepted' if it is deemed to have reached the required standards to proceed to public examination. Following the examination stage, the Secretary of State for Energy and Climate Change will determine the application.

The application consists of a sea wall of 9.5km constructed using core and sediment filled geotubes with rock armour bund. The sea wall will create a lagoon impounding an area of 11.5km2  At one end of the sea wall, 16 turbines and 10 sluice gates will be housed.