The UK electricity grid is undergoing its most significant reform in decades. What was once a largely technological challenge has become of defining issues for economic growth, industrial strategy, housing delivery, data centre of development and the transition to net zero.
At the heart of problem lies a grid connection queue which has expanded beyond 700gw of projects, roughly four times the capacity required to meet Britain’s 2030 clean power ambitions. Long waiting times, sometimes extending beyond ten years, have created a system where viable projects have been delayed while speculative developments have been seen to “fog” what is in truth very limited network capacity.
The response has been a fundamental shift away from the traditional “first come, first served” model towards a “first ready and needed” approach. This approach has been led by the National Energy System Operator (NESO), supported by Ofgem and the Government.