On January 30, 2020, the Federal Energy Regulatory Commission
("FERC"), in a 2-1 vote, issued an order on condemnation rights of natural gas
companies that hold a certificate of public convenience and
necessity under section 7(h) of the Natural Gas Act
("NGA"),1 which
may have wide-reaching effects for interstate natural gas pipeline
companies, end-users of natural gas, and their investors. On May
21, 2020, FERC upheld its interpretation by issuing an order denying rehearing, in a 3-1 vote. As
described below, FERC's decision conflicts with recent court
action and is being tested in pending litigation.
Background
In the latter part of 2019, the U.S. Court of Appeals for the
Third Circuit issued an order barring PennEast Pipeline Company,
LLC ("PennEast") from condemning state-owned land in New
Jersey to build an interstate natural gas pipeline.2 FERC issued a certificate of
public convenience and necessity to PennEast in early 2018,3 which automatically