The Infrastructure Planning Commission (IPC) has published a letter on its website announcing that it has rejected changes to a scheme that was before the IPC for consideration - the Brig-y-Cwm energy from waste generating facility.

United KingdomEnergy and Natural Resources
Stephen Collings
Stephen Collings
Paul Wootton
Paul Wootton

The Infrastructure Planning Commission (IPC) has published a letter on its website announcing that it has rejected changes to a scheme that was before the IPC for consideration - the Brig-y-Cwm energy from waste generating facility. Please click here to view this letter.

Post-submission of the application, Covanta sought to refine its design by reducing the quantity of spoil removal required (in response to consultees' concerns raised post-submission on the sustainability of significant spoil removal). This was to be achieved by reducing the excavation undertaken and raising the base foundation for the development, apparently by up to 3m on some parts of the site.

The IPC refused to accept the consequential amendments to the application because: