Yuanda (UK) Co Ltd v WW Gear Construction Limited [2010] EXHC 720 (TCC)

This article is the first of a two part note on the recent decision in Yuanda v WW Gear. It deals with the late payment of interest under the Late Payment of Commercial Debts (Interest) Act 1998 (see issue (a) below).

United KingdomCorporate/Commercial Law

This article is the first of a two part note on the recent decision in Yuanda v WW Gear. It deals with the late payment of interest under the Late Payment of Commercial Debts (Interest) Act 1998 (see issue (a) below). Part two will appear in the next week and will address the issue of reasonableness under the Unfair Contract Terms Act 1997 (see issue (b) below).

What are the facts?

A trade contractor, Yuanda (UK) Co Limited (Yuanda) engaged WW Gear Construction Limited (Gear) to provide glazed curtain walling to the GLC building by Westminster Bridge, which was being developed into a luxury hotel.

Gear prepared a package of contract documents, to be issued to trade contractors and used as a starting point for negotiations. The package was based on the JCT standard form building contract (JCT Contract), which is often used in the construction industry, but with a number of amendments contained in a separate schedule of amendments. Following