In the case of Mott MacDonald Ltd v Trant Engineering
Ltd [2021] EWHC 754 (TCC), the TCC confirmed by way of summary
judgment that there would be no presumption that a party who
"deliberately and wilfully" breaches a contract cannot
rely on an exclusion clause. To exclude such breaches specifically,
the wording of a clause must be clear.
Background
This case was part of the second round of litigation between the
parties to reach the TCC. Both disputes arose out of a project to
build a power station on the Falkland Islands. Mott MacDonald (MM)
provided design consultancy services to Trant Engineering (Trant)
as a part of its tender submission. Trant was awarded the contract
and shortly after, a dispute broke out between MM and Trant
concerning the scope of works and payment. This dispute ultimately
led to MM revoking Trant's access to the shared project
software, which was, at the time, implemented and controlled by MM.
Trant sought an interim injunction to allow it