Shipbuilding Contracts – Limitation Periods And Sale Of Goods Act

In Neon Shipping Inc. v. Foreign Economic 7 Technical Corporation Co. of China and another [2016] EWHC 399 (Comm) the Commercial Court dealt with an appeal from London arbitrators in a dispute arising out of a shipbuilding contract.

United KingdomCorporate/Commercial Law

In Neon Shipping Inc. v. Foreign Economic 7 Technical Corporation Co. of China and another [2016] EWHC 399 (Comm) the Commercial Court dealt with an appeal from London arbitrators in a dispute arising out of a shipbuilding contract ("SBC").

The time bar issue

The SBC provided in Article XI that:

Article XI Guarantee

1. Guarantee

Seller guarantees that Vessel, and all parts thereof that [are] manufactured or supplied by Seller, its sub-contractors and/or vendors under this Contract, will be seaworthy and contractual in all respects, and will be free from all defects which are due to defective design, construction, calculation, material or workmanship (collectively "Guarantee Defects"), upon delivery and for a period of twelve (12) months from the Date and Time of Delivery ("Guarantee Period").