The Supreme Court has given judgment in RTI Ltd
v MUR Shipping BV [2024] UKSC 18 on the interpretation of
a force majeure clause in a shipping contract containing a proviso
that parties are to make reasonable endeavours to overcome the
force majeure event. In unanimously allowing the appeal, it
concluded that such proviso does not oblige parties to accept an
offer of non-contractual performance – even where this would
achieve the same result as contractual performance and cause no
detriment. The decision has general application to force majeure
clauses in all commercial contracts.
Background
The appellant shipowner MUR Shipping BV
(“MUR”) entered into a contract of
affreightment with the respondent charterer RTI Ltd
(“RTI”) on an amended Gencon form
voyage charterparty for a monthly shipment of bauxite from Guinea
to Ukraine. It was agreed that RTI would make monthly payments to
MUR in USD.