Share on LinkedInShare on LinkedIn

ARTICLE · 01 MAY 2012

Notices To Complete

Standard residential and commercial property contracts will contain provisions dealing with what happens if either party fails to complete.

United KingdomCorporate/Commercial Law
Will Oakes
Will Oakes

Standard residential and commercial property contracts will contain provisions dealing with what happens if either party fails to complete. The initial step where breach occurs is for the non-defaulting party to serve a notice to complete. This then gives the defaulting party usually 10 working days to rectify the breach. If rectification does not take place within the 10 day period then the non-defaulting party shall be entitled to rescind the contract.

A recent Court of Appeal decision on Oakglade Investments Ltd and another v Dhand [2012] EWCA Civ 1986 considered whether a seller was ready, able and willing to complete when it service a notice to complete on a buyer.

In this case the contract provided that the seller would auction three residential properties and if they did not reach a reserve price then the buyer would acquire these properties at an agreed price. The sellers served a notice to complete at a higher price than that in the contract claiming that