ARTICLE · 30 SEPTEMBER 2014

Liquidated Damages: When To Assess Whether They Are A "Genuine Pre-Estimate Of Loss"

Ensuring your rates of liquidated damages are a "genuine pre-estimate of loss" is no longer enough to ensure that they will not later be held to be a penalty.

United KingdomCorporate/Commercial Law

Ensuring your rates of liquidated damages ("LADs") are a "genuine pre-estimate of loss" at the time you enter into a construction contract is no longer enough to ensure that they will not later be held to be a penalty and therefore unenforceable.

In Unaoil Ltd v Leighton Offshore Pte Ltd [2014] EWHC 2965 (Comm) a rate of LADs was agreed between the parties in relation to a contract which was subsequently varied and the value of the contract reduced. No change was made to the agreed rate of LADs at the time of the variation. Eder J in the Commercial Court held that even though the agreed rate of LADs may have been a genuine pre-estimate of loss at the time of the contract, the rate of LADs was penal and therefore unenforceable as the agreed rate of LADs could not have been a genuine pre-estimate of the losses which might be suffered under the varied contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from