In a recent decision, the Court of Appeal held that a clause
providing for liquidated damages for delay did not apply where the
contractor failed to complete the contracted work (the installation
of a new software system). The employer under the contract was
therefore entitled to recover damages for breach assessed on
ordinary principles, rather than liquidated damages: Triple Point
Technology Inc v PTT Public Company Ltd [2019] EWCA Civ
230.
The Court of Appeal said that the question of whether such a
clause applied in these circumstances would depend on the wording
of the clause itself. In relation to the specific clause before the
court, the clause was focused specifically on delay between the
contractual completion date and when the work was actually
completed by the contractor and accepted by the employer. If that
never occurred, the liquidated damages clause did not apply. The
case is a useful reminder that, when drafting a liquidated damages
clause, it is