Liquidated damages (LDs) are predetermined damages set when a
contract is entered into, based on a calculation of the estimated
loss likely to be incurred if the contractor fails to meet specific
dates. LDs clauses are commonplace in commercial contracts. In
construction contracts, they generally apply where the contractor
fails to complete works by specified dates due to reasons for which
the contractor is culpable. They are generally calculated according
to the period between the specified dates and actual completion.
But what happens if the contractor does not reach
completion?
In the recent case of Triple Point Technology v PTT
Public Company Ltd (PTT) the Supreme Court required
to determine whether, and if so to what extent, LDs apply in the
circumstances where a contractor fails to complete works and a
second contractor is brought in.