In 2014, the High Court and Appeal Court of Northern Ireland considered one of very few cases where an NEC3 contract was the underlying contract at the heart of the dispute.

United KingdomCorporate/Commercial Law

In 2014, the High Court and Appeal Court of Northern Ireland considered one of very few cases where an NEC3 contract was the underlying contract at the heart of the dispute.

The same parties, the Northern Ireland Housing Executive (NIHE) and Healthy Buildings (Ireland) Limited (HBI), were back before the High Court in Northern Ireland again recently, and the case has resulted in another judgment that will be of interest to those using the NEC3 in England and Wales.

Background

Back in 2012, the parties entered into two contracts on a modified NEC3 Professional Services Contract (PSC) whereby HBI was to provide certain services to NIHE regarding the assessment of presence of asbestos in homes owned by NIHE (which is a public sector landlord).