Oral Variations And The Right To Payment In International Construction Contracts: A Strict Approach In Singapore

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

FIDIC ("International Federation of Consulting Engineers") Contracts do not exclude a right to time and money if the Employer or Engineer instructs a Variation only orally.

SingaporeLitigation, Mediation & Arbitration

FIDIC ("International Federation of Consulting Engineers") Contracts do not exclude a right to time and money if the Employer or Engineer instructs a Variation only orally. The FIDIC Red Book for example at Clause 3.3 allows "instructions" that are given orally but if such instruction is a Variation, the Contractor will need to give notice under Clause 20.1 to get additional time and/or money. Bespoke amendments to the FIDIC forms of contract typically seek to exclude rights to additional time and money by making it express that only Variations instructed, notified or requested in writing by the Engineer allow recovery of time and/or money. The High Court in Singapore has endorsed this tough approach. Vim Engineering Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd [2021] SGHC 63, will now be cited by many in International Construction Arbitration to support the proposition that where a contract expressly provides that a variation shall be carried out "only" pursuant

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from