Since the reopening of non-essential construction sites from 18
May, some contractors are reporting that works are progressing at a
slower rate due to compliance with the Return to Work Safely
Protocol. If delay claims arise a recent Australian case is a
timely reminder to both contractors and employers of the importance
of maintaining site records in substantiating or defending delay
claims.
In the White Construction Pty Limited v PBS Holding
Pty Limited [1] the plaintiff contractor
brought a delay claim against two of its sub-contractors. The
Australian New South Wales Supreme Court addressed the evidence
required to prove delay claims in construction disputes. The case
may persuade an Irish court, arbitrator or adjudicator to take a
similar approach. In deciding against the plaintiff, the court
analysed the alleged delay claim using an “open-textured
approach” which meant that it looked at the contemporaneous
records of progress during the works (such as the site