PWC: Adjustments To Contract Sum (Part 2)

William Fry LLP
William Fry LLP
Contributor
William Fry LLP

William Fry LLP

William Fry advises leading Irish and international companies, covering both the public and private...

View firm profile
Explore more from William Fry LLP

This article examines the mandatory Clause 10.6 valuation hierarchy under the Public Works Contract, exploring how adjustments to contract sums are calculated through rate-based and cost-based methods. It analyzes the legal framework governing variations, from contractual valuation rules through to residual remedies of fair valuation and quantum meruit, with particular attention to preliminary overheads and the procedural discipline required of employers and Employer's Representatives.

IrelandReal Estate and Construction

Valuation, Fair Pricing, and Practical Takeaways: Legal Issues

The mandatory Clause 10.6 valuation hierarchy governs adjustments to the contract sum, with fair valuation and quantum meruit available only as residual remedies for employers and Employer’s Representatives (ERs).

Introduction

In Part 1 of this series, we examined the conceptual framework for variations, the elements of a valid variation, the valuation starting position, and the claims procedure, which serves as the gateway to valuation. Part 2 examines the mandatory Clause 10.6 valuation hierarchy, cost-based valuation, the residual remedies of fair valuation and quantum meruit, preliminary overheads, and practical takeaways for employers and ERs.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from