PWC: Adjustments To The Contract Sum (Part 1)

William Fry LLP
William Fry LLP
Contributor
William Fry LLP

William Fry LLP

William Fry advises leading Irish and international companies, covering both the public and private...

View firm profile
Explore more from William Fry LLP

Construction contracts under the Public Works Contract establish a rigorous procedural framework that contractors must navigate before any valuation of variations or compensation events can occur. This analysis examines the critical distinction between establishing entitlement through proper claims procedures and the subsequent valuation process, exploring how failure to comply with notice requirements and conditions precedent can bar claims regardless of their underlying merit.

IrelandReal Estate and Construction

A contractor must comply with the contractual claims procedure before any assessment of valuation adjustments under the Public Works Contract (PWC). We examine the framework for testing entitlement before valuation.

Introduction

The PWC provides a structured mechanism for adjusting the contract sum in response to variations and compensation events. Clause 10.6 sets out a valuation hierarchy that governs how adjustments to the contract sum arising from compensation events are to be assessed. It is important for the employer and Employer’s Representatives (ERs) to recognise that before any question of valuation arises, a contractor must first navigate the significant procedural requirements set out in Clause 10.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from