The Emergency Measures in the Public Interest (Covid-19) Act
2020 (the 2020 Act) was signed into law on 27 March 2020. Part 3,
Section 9 of the 2020 Act and related regulations introduce a
number of changes to our planning and building control system. The
section in question is not lengthy but its impact is wide ranging
and requires careful review in applying the changes to specific
cases. A key tip for planning applicants, their advisors and the
public is to have a calendar to hand when working out the impact of
the changes on projects.
Extension of time periods – planning applications
In normal circumstances, a planning authority has eight weeks
within which to determine a planning application1. The
public can make submissions on a planning application at any time
within five weeks from the date the planning authority receives it.
The 2020 Act extends these timeframes (and others) as a result of
the Covid-19 public health crisis by the insertion of a new