NHAI, vide circular dated
July 8, 2024, issued a policy circular issuing standard operating
procedures (“SOPs”) which the
authority engineers/independent engineers appointed under the
concession agreements must follow while appointing third
party/replacement contractors for carrying out works which were not
duly performed by the concessionaire/delays caused by
concessionaire in completing such works, at the risk and cost of
the original contractor/concessionaire. The policy circular, at the
outset, specifies that the SOP would be applicable for Engineering
Procurement Construction (“EPC”),
Hybrid Annuity Mode (“HAM”), Build
Operate Transfer (“BOT”), Toll Operate
Transfer (“TOT”) and item rate
contracts/concession agreements. The object and purpose of issuing
these SOPs are as follows: