Clarification On Exemption From Project Registration And Interpretation Of Commencement And Completion Certificate

Recently, the Maharashtra Real Estate Regulatory Authority ("MahaRERA") has issued an Order bearing No.62/2024 on October 22, 2024 ("Order") clarifying the following important issues...

IndiaReal Estate and Construction

Recently, the Maharashtra Real Estate Regulatory Authority ("MahaRERA") has issued an Order bearing No.62/2024 on October 22, 2024 ("Order") clarifying the following important issues:

1. Projects for which registration is not compulsory;

2. What constitutes commencement certificate and completion certificate in case of plotted developments.

Where Registration of Real Estate Project is not compulsory:

1. With respect to Section 3(2)(a) of the Real Estate (Regulation and Development) Act, 2016 ("RERA Act"), the MahaRERA has clarified that:

1. a real estate project shall not require registration if the area of land proposed to be developed is less or equal to 500 (five hundred) square meters irrespective of the number of units/apartments proposed to be developed even if the apartments/units to be developed in all phases exceed 8 (eight);

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This insight/article is intended only as a general discussion of issues and is not intended for any solicitation of work. It should not be regarded as legal advice and no legal or business decision should be based on its content.

See more popular content from