Share on LinkedInShare on LinkedIn

ARTICLE · 08 APRIL 2025

Whether Period Of 30 Days As Provided In Section 34(3) Of The Arbitration & Conciliation Act, 1996 Is Condonable? Supreme Court Answers In Negative: An Analysis Of Hon'ble Supreme Court's Decision In ‘My Preferred Transformation & Hospitality Pvt. Ltd. And Another vs. Faridabad Implements Pvt. Ltd.'

S&A Law Offices
S&A Law Offices
Contributor
S&A Law Offices

S&A Law Offices

S&A Law Offices is a full-service law firm headquartered in Delhi NCR. The firm has 300+...

View firm profile
Explore more from S&A Law Offices

The appellants entered into lease agreements with the respondent, the property owner. Following disputes, the respondent invoked arbitration, resulting in an arbitral award in its favor on 04.02.2022.

IndiaLitigation, Mediation & Arbitration

Background of the case: The appellants entered into lease agreements with the respondent, the property owner. Following disputes, the respondent invoked arbitration, resulting in an arbitral award in its favor on 04.02.2022. The appellants received a scanned copy of the award on the same day and a signed hard copy on 14.02.2022, marking the start of the limitation period. The three-month limitation under Section 34(3) expired on 29.05.2022, with a further 30-day condonable period ending on 28.06.2022. This fell during the High Court's summer vacation (04.06.2022 to 03.07.2022). The appellants filed the Section 34 petition, along with an application for condonation of delay, on 04.07.2022, the day the court reopened, in line with a notification from the Delhi High Court on 20.05.2022. Meanwhile, the respondent-initiated execution of the award.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from