The Hon'ble Supreme Court in a recent judgment in
Welspun Specialty Solutions Ltd. (formerly known as Remi Metals
Gujrat Ltd.) v. Oil and Natural Gas Corporation
Ltd.1 held that whether time is of the essence in a
contract has to be culled out from the reading of the entire
contract as well as the surrounding circumstances. Merely having an
explicit clause may not be sufficient to make time the essence of
the contract. In this article, we briefly discuss the facts and
circumstances which led to the aforementioned judgment of the
Hon'ble Supreme Court.
Brief Facts
A global tender was floated by ONGC for purchase of seamless
steel casing pipes. Remi Metals Gujrat Ltd., now known as Welspun
Specialty Solution Ltd. ("Remi Metals"),
emerged as the successful bidder. Remi Metals claimed that it had
to bid to supply pipes as a supplier on behalf of Volski Tube
Mills, Russia. In the tender, four purchase orders were issued
which mentioned that the delivery period would