1. Introduction
1.1 In National Highway Authority of India v. T. Younis & Anr., 2026 INSC 616, the Hon'ble Supreme Court of India (“SC”) has reaffirmed and clarified its previous decisions on the interaction between Sections 33 and 34(3) of the Arbitration and Conciliation Act, 1996 (“A&C Act”), bearing implications over the post-award remedial landscape.
1.2 This decision gains importance since it holds that the deferment of the limitation period under Section 34 of the A&C Act, upon the filing of a Section 33 application by a party, is agnostic to the nature and outcome of the application.
1.3 The authors, in the present case comment, seek to briefly discuss the highlights of this decision and its practical implications.