Introduction
The Delhi High Court in a judgement dated November 20, 2024,
reiterated the law of on section 34 of the Arbitration and
Conciliation Act, 1996.
The present case involves Indian Oil Corporation Ltd. (IOCL) and
Fiberfill Engineers, with IOCL filing an appeal under Section 37 of
the Arbitration and Conciliation Act, 1996, against an order passed
by the learned Single Judge in a petition filed by Fiberfill under
Section 34 of the same Act to withhold the amount as liquidated
damages against the breach.1
Dispute Background:
The dispute arose from an agreement dated January 11, 2007, for
designing, supplying, installing, testing, and commissioning high
mast signage systems at various IOCL retail outlets in Tamil Nadu
and Pondicherry. There was a delay in completion of work due to
which as per the contract clause 4.2.2.0 IOCL retained Rs.
22,08,528 as liquidated damages/ penalty. The Fiberfill initiated
arbitral proceedings and filed claims for