This decision sends a strong pro-arbitration message to all Parties and highlights the importance of compliance with a peremptory order of the Tribunal.

IndiaLitigation, Mediation & Arbitration

In a recent decision rendered by the Queen's Bench in the case of Swallowfalls Limited v. Monaco Yachting & Technologies S.A.M. and ANR, it has been re-iterated that the dismissal of claims by the Tribunal on account of failure of a Party to provide security for costs is final and binding. The claims cannot be brought up subsequently in Court despite the fact that they were dismissed without any discussion as to their merits.

Facts Of The Case:

The dispute arose out of a construction contract entered into in 2006 for the construction of a 71.5m luxury yacht that the Claimant had commissioned from the Defendants. It was, however, understood between the Parties that the actual construction would be sub-contracted to Cantiere San Marco SRL, in Italy. The total consideration for the yacht was Euro 35, 231, 6000, to be paid in 11 instalments which were linked to the construction of the yacht.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from