Share on LinkedInShare on LinkedIn

ARTICLE · 24 JANUARY 2020

Supreme Court: Difference Between Inadequacy Of Reasons In Arbitral Award And Unintelligible Awards

The sole objection herein, was with reference to claim No. (2), that is, with respect to losses due to unproductivity of the men and machineries.

IndiaLitigation, Mediation & Arbitration

Article by Vijay Pal Dalmia, Advocate, Supreme Court of India and Delhi High Court, Partner & Head of Intellectual Property Laws Division, Vaish Associates Advocates, India

The Supreme Court of India ("SC") has vide its judgment dated December18, 2019 ("Judgment"), highlighted the difference between inadequacy of reasons in an arbitral award and unintelligible arbitral awards passed under the Arbitration and Conciliation Act, 1996 ("Act").

Facts

DCM Shriram Aqua Foods Limited ("DCM") had entered into a contract ("Contract") with M/s. Crompton Greaves Limited ("Respondent") for the construction of an aquaculture unit by the former. Pursuant to the said Contract, the Respondent, on behalf of DCM, invited tenders for carrying out certain works for construction of ponds, channels, drains and associated works ("Project"). M/s. Dyna Technologies Private Limited ("Appellant") gave its proposal, estimate and quotation for carrying out the Contract. Thereafter,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

© 2026, Vaish Associates Advocates,
All rights reserved
Advocates, 1st & 11th Floors, Mohan Dev Building 13, Tolstoy Marg New Delhi-110001 (India).

The content of this article is intended to provide a general guide to the subject matter. Specialist professional advice should be sought about your specific circumstances. The views expressed in this article are solely of the authors of this article.

See more popular content from