In the recent case of Rohan Builders vs. Berger Paints ("Rohan Builders Case"), the Hon'ble Supreme Court of India ("Supreme Court") has conclusively settled...

IndiaLitigation, Mediation & Arbitration

In the recent case of Rohan Builders vs. Berger Paints1 ("Rohan Builders Case"), the Hon'ble Supreme Court of India ("Supreme Court") has conclusively settled the long-standing issue concerning the time of filing an application for extension of time to render an arbitral award under Section 29A of the Arbitration and Conciliation Act, 1996 ("Arbitration Act"). While deciding the issue in the affirmative, the Supreme Court ruled that such an application can be filed even after the expiry of the prescribed time period.

Background

Under Section 29A of the Arbitration Act, arbitral awards in domestic arbitrations must be delivered within 12 (twelve) months from the date of completion of pleadings2. This time period can be extended by another 6 (six) months by the consent of the parties. If the arbitral tribunal is unable to pass the award within this time period of 12 (twelve) months (or 18 (eighteen) months, where parties have consented to the 6

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.