The Hon'ble Supreme Court in a recent judgment of Universal
Petro Chemicals Ltd v. B. P. PLC and Others1 had the
occasion of dealing with the ambit of Section 21 of the Specific
Relief Act, 1963 ("the Act")
vis-à-vis a claim for damages in addition to a claim for
specific performance. In that context the Hon'ble Supreme Court
examined the statutory requirement of the necessity of pleadings to
sustain the grant of damages/compensation. This article endeavors
to highlight the observations of the Hon'ble Supreme court from
the perspective of Section 21 of the Act.
STATUTORY BACKDROP:
Section 21 of the Specific Relief Act, 1963 provides that the
plaintiff may also claim compensation for breach of performance by
Defendant, in addition to claim for specific performance of a
contract. Section 21 provides that Court may grant compensation in
a suit if the court decides that specific performance ought not to
be granted but there is a contract between the parties which