INTRODUCTION
The most commonly encountered claims, raised by Contractors
against employers in a construction dispute are claims for
‘loss of profit' (on account of unexecuted
work) and ‘loss of profitability' (on account
of prolongation of the period of contract). Although a plethora of
judgements of the Supreme Court and various High Courts deal with
the requirement of proof and computation under these distinct heads
of claims, they are oft-conflated by the Indian courts, despite
there being fundamental differences between the two.
It's a trite position of law that where it is possible to
prove actual damage or loss, such proof is not dispensed with and
the contractor must establish actual loss in order to sustain the
claim for loss of profit.1