ARTICLE · 05 NOVEMBER 2024

In Search Of Lost 'Court': Analysing The Interpretative Ambiguities Under Section 29A Of The Arbitration Act

S&A Law Offices
S&A Law Offices
Contributor
S&A Law Offices

S&A Law Offices

S&A Law Offices is a full-service law firm headquartered in Delhi NCR. The firm has 300+...

View firm profile
Explore more from S&A Law Offices

The question of what is ‘Court' under Section 29A has been the subject of debate but was believed to be settled by the Hon'ble Supreme Court in a recent decision in

IndiaLitigation, Mediation & Arbitration
Saksham Chaturvedi
Saksham Chaturvedi
Neelabh Niket
Neelabh Niket
Author LinkedIn connections

Introduction

Section 29A(4) of the Arbitration and Conciliation Act, 1996 (for brevity "the Act") stipulates that the mandate of the arbitral tribunal shall be terminated if the arbitral award is not made within the time prescribed under sub-section (1) or (3) of Section 29A. The statutory time frame for rendering the arbitral award may be extended where the award has not been delivered within 12 months from the completion of pleadings, or within the additional 6-month period under Section 29A(3). Such an extension under Section 29A(4) can be sanctioned by the 'Court' basis on an application under Section 29A(5) by either party, where the application is demonstrative of sufficient cause.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from