By a recent judgment, the Division Bench of the High Court of
Delhi (“Delhi HC”) in the case
of Cobra Instalaciones Y Servicios v. Haryana
Vidyut Prasaran Nigam Ltd.1 upheld
the Arbitral Tribunal's quantification of liquidated damages
on the basis of “honest estimations” and “rough
methods” to arrive at a fair assessment of damages in a case
where the quantification was complex and there was insufficient
evidence on record.
Brief Facts
Haryana Vidyut Prasaran Nigam Ltd
(“Respondent”) awarded a contract to
Cobra Instalaciones Y Servicios
(“Appellant”) to design, supply, and
install sub-stations for the Haryana Power System Improvement
Project (“Project”). The contract
stipulated a 450 (four hundred and fifty) day deadline and included
a clause for liquidated damages (“LD”)
in case of any delays.