The Hon'ble Supreme Court in its recent judgment in DLF
Home Developers Ltd. v. Rajapura Homes Pvt. Ltd. &
Anr.1 reiterated that the courts acting under
Section 11 of the Arbitration and Conciliation Act, 1996
(Arbitration Act) are not expected to act
mechanically merely to deliver a dispute at the doors of an
arbitrator. On the contrary, the courts are obliged to apply their
mind to the core preliminary issues, albeit, within the framework
of Section 11 of the Arbitration Act. Such a review, is not
intended to usurp the jurisdiction of the arbitral tribunal, but is
rather aimed at streamlining the process of arbitration.
Resultantly, the Hon'ble Supreme Court held that even when an
arbitration agreement exists, the courts can decline a prayer for
reference under Section 11 if the dispute was not correlated to the
arbitration agreement. In this article, we briefly examine the
facts and findings in the aforesaid judgment.