Introduction
The settled position of law is that parties cannot contractually
limit the time within which arbitration can be initiated, which is
dictated by the provisions of The Limitation Act, 1963. A seminal
judgment in this regard is that of the Hon'ble Delhi High
Court in Municipal Corporation of Delhi vs. Natraj Construction
Company,1 which shall be analysed in this article.
Section 28 of the Indian Contract Act, 1872 (“ICA”) and
its 1997 amendment lies at the heart of this discussion.
Section 28 of the Indian Contract Act, 1872
Prior to its amendment in 1997, Section 28 of the ICA voided
agreements which restricted the limitation period for bringing a
claim to a period lesser than what was provided in The Limitation
Act, 1963. It did not provide anything in respect of agreements
which extinguished the right of a party to bring claims on expiry
of the contractually prescribed period of time. This led to the
courts distinguishing between agreements which